Please read the guidance below carefully before completing the application form. Particular attention should be paid to the minimum notice periods required by the Ayrshire Roads Alliance. Failure to fully comply with the requirements as set out below may result in delays in the application process. It is the responsibility of the applicant to ensure all required information is present and correct.
Guidance
- Temporary Traffic Restrictions such as road closures, short term parking restrictions and reduced speed limits are used to ensure that work on or adjacent to the public road can be undertaken safely.
- Temporary Traffic Restrictions can also be used to ensure the safe holding of or operation of events on or adjacent to the public road.
- It is the responsibility of the person promoting the works or holding the special event to ensure that all their necessary permissions are in place and that once approved that the restrictions, including any diversion route are signed safely and appropriately. The promotor is also fully responsible for publicising the restrictions, and notifying affected persons.
- Costs apply – these comprise a set fee for processing the application and advertising costs (for Order which require publication in the local press)
- Ayrshire Roads Alliance (ARA) require
- a minimum of 30 working days’ Notice to process and advertise a Traffic Regulation Order
- a minimum of 20 working days to process a Traffic Regulation Notice applicable for works of 5 days or less
- a minimum of 30 working days to process a Traffic Regulation Order applicable for Special Events
- Emergency Notices are processed as soon as is reasonably practicable within normal working hours
- Prior to completing your application please read the following guidance;
- ARA cannot process applications for restrictions on private roads or on the A77 or A78. The A77 and A78 are Trunk Road and are managed by Amey Highways on behalf of Transport Scotland.
- Applicants are required to have an LA reference No. and Scottish Roadworks Register (SRWR) before completing the application form. You will not be able to submit your application without these.
- Plans showing the extent of works and where applicable, diversion routes, should be to Chapter 8 standard and show Traffic Management signage. If plans are unclear or not to an acceptable standard the application can be rejected.
-
Applicants applying for restrictions to facilitate the holding of a special event must have contacted events@east-ayrshire.gov.uk or licensing@south-ayrshire.gov.uk prior to making their application. Colleagues in the events team can provide advice and guidance to ensure that your event is as safe and successful as possible.
- A PO number or other suitable recharge details are required before your application can be submitted
- Please review the existing planned restrictions to check for clashes before submitting your application.
Restrictions Map
Costs
East Ayrshire
East Ayrshire Council Charges |
2024/2025 |
|
|
Emergency Temporary Restrictions by Notice for 21 days max |
£612 |
|
|
|
Extend Emergency Notice by another Notice for 21 days max |
3 weeks notice period given
£674
|
2 weeks advance notice period given
£734
|
1 weeks advance notice period given
£795
|
|
Extend Emergency Notice by Order
Plus advertising costs
|
3 weeks notice period given
£817
|
2 weeks advance notice period given
£880
|
1 weeks advance notice period given
£942
|
|
Temporary Restrictions by Notice 5 days max *
Plus advertising costs
|
4 weeks notice period required
£595
|
3 weeks notice period given
£655
|
2 weeks notice period given
£714
|
1 weeks notice period given
£773
|
Temporary Restrictions by Order **
Plus advertising costs
|
6 weeks notice period required |
5 weeks notice period required |
4 weeks notice period required |
3 weeks notice period required |
2 weeks notice period required |
1 weeks notice period required |
One road restricted |
£629 |
£691 |
£754 |
£817 |
£870 |
£942 |
Two roads restricted |
£942 |
£1037 |
£1131 |
£1226 |
£1320 |
£1414 |
Three roads restricted |
£1256 |
£1382 |
£1508 |
£1634 |
£1760 |
£1884 |
Four roads restricted |
£1570 |
£1728 |
£1885 |
£2043 |
£2200 |
£2356 |
* Consideration will only be given to a shorter notice period when resources permit and this will be the exception to the rule of 4 weeks advance notice period for programmed works. If a Notice isissued in less than 4 weeks it will be subject to additional charges.
** Consideration will only be given to a shorter notice period when resources permit and this will be the exception to the rule of 6 weeks advance notice period for programmed works/events. If a TTRO is made in less than 6 weeks it will be subject to additional charges.
South Ayrshire
South Ayrshire Council Charges
|
2024/2025
|
|
5 Day Temporary Traffic order (by notice)
|
Charge per Order (please provide us at least 20 working days notice)
|
£653
|
Emergency Temporary Traffic order (by notice)
|
Charge per Order
|
£670
|
Temporary Traffic orders (advertised in press)
|
Charge per Order (plus advertising) Please provide us at least 30 working days notice
|
£690 +
advert cost
|
Section A - Billing
Billing Address
General Data Protection Regulation (GDPR)
Under GDPR, we now have to supply data subjects with Privacy Notices that contain significantly more information than previously
required under the Data Protection Act 1998. This is in order to meet new requirements about being transparent and providing
accessible information to customers/individuals about how you are going to use their personal data so that they are fully
informed and are aware of how they can exercise their rights under GDPR.
Section B - Applicants Details
Please provide emergency out of hours contact details.
Client Details
Section C - Restrictions
Which road is being restricted
When is the Temporary Traffic Restriction required to start and end?
If YES, then indicate the period over which the restriction has to be in place.
Please indicate why these restrictions are required:
Upload Plans
Other Traffic Authority
If the diversion is via another Traffic Authority's road other than East Ayrshire Council and South Ayrshire Council then you must provide confirmation that there consent has been given.
Please provide details of the person who consented on behalf of the Traffic Authority.
Section D - Public and School Transport Services
Before submitting your application form contact Strathclyde Partnership for Transport (SPT) at bus.operations@SPT.co.uk to find out if your works or temporary restrictions impact on public transport services and/or school transport.
Section E - Public Car Parks
Section F - Additional Information
The completion and submission of this application DOES NOT automatically grant approval